The short answer
Removing a tenant-built mezzanine, office pod, cool room or freezer room at lease end is a construction job. Check whether it needs a building permit, have power, plumbing, gas and fire services disconnected by licensed trades, have refrigerant recovered by a licensed refrigeration technician, check the asbestos register in older buildings, then remove the structure and repair the fixing points.
Last reviewed
Key takeaways
- 01Your lease and the landlord's original consent decide whether the structure must come out. The landlord or next tenant may want it kept, so ask in writing.
- 02In Victoria, demolition is building work and generally needs a permit. Removing a mezzanine changes floor area, so the usual alteration exemption does not cover it. In NSW, ask a certifier or your council.
- 03Refrigerant must be recovered by a technician who holds a refrigerant handling licence, before a cool room or freezer room is taken apart.
- 04Power, plumbing, gas and sprinklers must be disconnected by licensed or qualified trades before the structure is removed.
- 05In buildings from before the end of 2003, check the asbestos register before cutting, drilling or removing anything.
Mezzanines, office pods, cool rooms and freezer rooms are some of the biggest things a warehouse tenant adds. Taking them out at lease end is a construction job, not a clean-up. It can need a permit, licensed trades, refrigerant recovery and repairs to the slab and walls. This page explains what is involved and what to check first.
General information only, not legal advice. What you must do depends on the wording of your own lease. If the amount at stake is large or the landlord's demands look wrong, talk to a property lawyer.
Do I have to remove the structure at all?
Start with the documents:
- The make-good clause, and any clause about alterations or tenant works.
- The landlord's consent for the mezzanine, office pod or cool room. It may say whether it must come out at the end.
- The move-in condition report or photos. The Victorian Small Business Commission recommends agreeing a condition report at the start of a lease and keeping copies. It shows what was there before you.
- Any landlord make-good notice or schedule. Compare it line by line with the clause.
The NSW Small Business Commission describes make good as returning premises to the condition they were first built, the condition at the start of the lease, "or some other condition as specified in the lease". If a structure was already there when you moved in, it may not be yours to remove.
Can I leave it for the next tenant?
Sometimes. A mezzanine adds storage, an office pod can save an incoming tenant a fit-out, and a food or cold-chain business may want a working cool room. Ask the landlord before you pay to remove anything.
If the answer is yes, get it in writing. List what stays, its condition, and the services connected to it, with dated photos, so it cannot be raised as a make-good claim later.
Does removing a mezzanine or cool room need a permit?
It can, and you should find out before any work starts.
Victoria. "Building work" under the Building Act 1993 (s 3) includes demolition, and building work generally needs a permit (s 16). Schedule 3 of the Building Regulations 2018 exempts some alterations to commercial and industrial buildings from needing a permit, but that exemption does not cover work that changes floor area, removes load-bearing elements or affects an essential safety measure. Removing a mezzanine changes floor area. Sprinklers are a common essential safety measure. A building surveyor can confirm whether your job needs a permit.
NSW. Some internal commercial and industrial alterations may be exempt or complying development under the state planning codes, but the conditions are specific. Ask a registered certifier or your council before relying on that.
Permits take time. Raise this early: our warehouse make-good checklist puts the permit question 6 to 9 months before the lease ends.
Which services need to be disconnected first?
Structures often have services running through or under them. They must be disconnected properly before demolition starts.
| Service | What to ask for | Who does it |
|---|---|---|
| Power and lighting | Tenant circuits removed and made safe back to the switchboard | Licensed electrician |
| Data and comms | Cabling removed back to the agreed point | Data cabler |
| Plumbing and drainage | Basins, condensate and floor drains disconnected and capped | Licensed plumber |
| Gas | Lines disconnected and capped | Licensed gasfitter |
| Sprinklers and fire detection | Isolated and modified, with the base system left working | Fire services contractor approved by the landlord |
| Air conditioning and refrigeration | Refrigerant recovered before the equipment is disconnected | Licensed refrigeration technician |
In Victoria, a person must not carry out prescribed electrical work unless they hold the right licence (Electricity Safety Act 1998, s 38). The NSW Government says you must hold an electrical licence or certificate to do any electrical wiring work in NSW. Ask for licence numbers on the quotes and keep any certificates for your handover file.
The building's fire systems are normally the landlord's, so the landlord or their fire services contractor will usually want to approve or carry out any sprinkler work. Ask for written confirmation that the system was left working.
How is refrigerant recovered from a cool room or freezer room?
Before a cool room or freezer room is taken apart, the refrigerant in its system must be recovered. The Australian Refrigeration Council (ARCtick) runs the national refrigerant handling licence scheme for the Australian Government, and a licence is needed for work such as taking refrigeration and air-conditioning equipment out of service.
What to ask:
- Is the technician licensed, and what is the licence number?
- Will they recover the refrigerant before anything is cut or disconnected?
- What happens to the compressors, condensers and other equipment: reuse, sale or disposal?
The same applies to split systems in office pods.
What happens to insulated panels?
Cool rooms, freezer rooms and some office pods are built from insulated panels. At removal they are unbolted or cut apart and taken off site for reuse, recycling or disposal.
Ask each quote to say how the panels will be dealt with and to provide disposal records. If the panels are in good condition, ask whether the landlord or another business might want them.
Check the original consent and drawings to see whether anything was built into or onto the slab under a cool room or freezer room, and ask the contractor how the floor will be left.
Mould can turn up in cool rooms. If you find it, an occupational hygienist can assess it.
Is there asbestos to check for?
Older industrial buildings, and older fit-outs inside them, can contain asbestos. Before refurbishment or demolition work, the person who manages or controls the workplace must check the asbestos register and update it if it is not adequate for the work (Victoria, OHS Regulations 2017, regs 240 and 241). SafeWork NSW says an asbestos register is required for workplaces built before 31 December 2003, or where asbestos has been found.
In both states, removing any friable asbestos needs a licensed removalist, and so does removing more than 10 m² of non-friable asbestos (in Victoria, also any job taking more than one hour in a 7-day period). You cannot tell asbestos by looking. Ask the landlord for the register before contractors quote, and give it to every one of them. See asbestos and hazardous materials at make good.
How are fixing points and the building repaired?
Once a structure is gone, it leaves marks:
- Anchor and base plate holes in the slab, filled with repair mortar. See warehouse floor restoration for methods and colour matching.
- Fixings in walls, columns and portal frames, removed and patched, and repainted where the lease requires.
- Penetrations through walls or the roof for refrigeration lines, flues or drains, sealed.
- Slab cuts or pits for drains or freezer floors, infilled if the lease requires the slab to be reinstated.
Check the move-in photos so you only repair what you changed.
What should I ask in a quote?
Get two or three itemised quotes against the same scope, from contractors who have inspected the site. Ask each one to show:
- who answers the permit question and who applies for any permit;
- service disconnections by trade, with licence numbers;
- refrigerant recovery as a separate line;
- demolition, panel disposal and waste;
- repairs to the slab, walls and penetrations;
- the program, exclusions, provisional sums and GST.
How much does it cost?
We do not publish a price. When we searched in October 2026, we found no free, published Australian source for industrial make-good rates.
What drives the cost:
- Size and construction of the mezzanine, pod or room.
- Permits, and any engineering or surveyor input.
- Services connected to the structure, including sprinklers.
- Refrigerant recovery and equipment removal.
- Asbestos, if the register or a survey finds it.
- Repairs the lease requires once the structure is gone.
Melbourne and Sydney industrial areas
See warehouse make good in Melbourne, including Dandenong, Truganina and Laverton, and warehouse make good in Sydney, including Eastern Creek, Silverwater and Alexandria. Racking coming out too? See racking removal. For the whole job, start with warehouse make good.
How MAKE GREAT helps with mezzanine and cool room removal
- Tell us about the site. Upload the lease, the landlord's consent for the structure, any landlord notice, a floor plan and photos.
- Lease check. Our lease check reads the make-good clause and drafts a preliminary list of likely works. It is a starting point only: a person at MAKE GREAT reviews it, and a contractor must confirm the scope on site.
- We send a structured brief to independent industrial contractors we have checked (ABN, insurance, and licences for trades that need them; see how we vet contractors) in your area.
- Compare itemised quotes side by side against the same scope, and choose who you want. You contract directly with the contractor.
How we are paid: Free for tenants. If you hire a contractor through us, they pay us a referral fee. Nobody can pay to rank higher. You are never obliged to accept a quote.
Ready to start? Use Check my lease, free to upload your lease and the landlord's make-good list.
Frequently asked questions
Do I have to remove the mezzanine I built?
Usually yes, if you built it, unless the lease or a written agreement with the landlord says it can stay. Check the landlord's consent for the mezzanine too, because it may say what must happen at the end of the lease. Some landlords or incoming tenants want a mezzanine kept, so ask before you pay to remove it.
Does removing a mezzanine need a building permit?
It can. In Victoria, demolition is building work under the Building Act 1993 and generally needs a permit. The permit exemption for some alterations to commercial and industrial buildings does not cover work that changes floor area, removes load-bearing elements or affects an essential safety measure. Ask a building surveyor (Victoria) or a certifier or your council (NSW) first.
Who removes the refrigerant from a cool room?
A technician who holds a refrigerant handling licence. The national licence scheme is run by the Australian Refrigeration Council (ARCtick) for the Australian Government, and a licence is needed for work such as taking refrigeration and air-conditioning equipment out of service. Ask for the technician's licence number on the quote.
What happens to the insulated panels from a cool room?
They are taken apart and removed from site for reuse, recycling or disposal. Before any panel is cut or removed in an older building, check the asbestos register. Ask each quote to say how the panels will be dealt with and to provide disposal records.
Can I leave a cool room or office pod for the next tenant?
Only with the landlord's written agreement. List what stays, its condition and the services connected to it, with photos, so it cannot be raised as a make-good claim later. A food business moving in may want a working cool room, so it is worth asking.
How much does mezzanine or cool room removal cost?
We do not publish a price. When we searched in October 2026 we found no free, published Australian source for industrial make-good rates. Cost depends on the size and construction of the structure, permits, the services connected to it, refrigerant recovery, panel disposal and the repairs the lease requires. Compare itemised quotes against the same scope.
Sources
Primary sources we checked when writing this page. Laws and guidance change, so check the current version.
- 1.Building Act 1993 (Vic), s 3 and s 16 (opens in a new tab)
- 2.Building Regulations 2018 (Vic), reg 23 and Schedule 3 (opens in a new tab)
- 3.Australian Refrigeration Council (ARCtick), national refrigerant handling licence scheme run for the Australian Government (opens in a new tab)
- 4.Electricity Safety Act 1998 (Vic), s 38 (opens in a new tab)
- 5.NSW Government, Electrical licences (opens in a new tab)
- 6.Occupational Health and Safety Regulations 2017 (Vic), asbestos regs 240 to 265 (opens in a new tab)
- 7.SafeWork NSW, Asbestos (opens in a new tab)
- 8.NSW Small Business Commission, NSW Retail Tenancy Guide (Jan 2024), glossary and end-of-lease sections (opens in a new tab)